Issue - decisions

Regeneration Pipeline Programme – Chesterfield-Staveley Regeneration Route

06/04/2023 - Regeneration Pipeline Programme

RESOLVED: to

 

1)    Note the progress being made on the preparation of the Chesterfield-Staveley Regeneration Route;

 

2)    Approve in principle the carrying out of further consultation and delegate authority to the Executive Director for Place, in consultation with the Cabinet Portfolio Holder for Infrastructure and Environment to agree the format and timing of this;

 

3)    Note the need for the allocation of up to £1.8million from the Regeneration Kick Start Fund to cover essential work before Cabinet next receives a report on the project, expected to be in September 2023; and

 

4)    Approve in principle the acceptance of grant funding towards project preparation and delegate authority to the Director of Finance and ICT to review terms and conditions and to accept grant funding of up to £7.3 million.