Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Report of the Director of Finance &
ICT
RESOLVED to:
1) Note the current position on the monitoring of Capital schemes;
2) Approve the funding change for the Amber Valley Rationalisation project;
3) Approve the addition of £56.930m as set out in paragraph 4.7 of the report to the capital programme to be funded from borrowing; and
4) Approve the addition of £3.393m as set out in paragraph 4.8 7 of the report to the capital programme to be funded from council resources.
Report author: Wendy Round
Publication date: 14/03/2024
Date of decision: 14/03/2024
Decided at meeting: 14/03/2024 - Cabinet
Effective from: 22/03/2024
Accompanying Documents: