Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To update Cabinet
RESOLVED to:
1) Accept the responses to the public consultation events held for the A5012 Via Gellia Safer Roads Fund (SRF) project and on-going consultation with statutory consultees;
2) Accept the scope of works recommended to be procured which may vary from those consulted upon and agreed with the Department for Transport (DfT) in December 2022;
3) Accept the strategy for procuring the works through the County’s internal Highway and Construction Services Team;
4) Accept the anticipated installation costs for each proposed safety interventions for the A5012 Via Gellia route;
5) Give authority for officers to work within the overall budget for the three SRF projects to a confirmed value of £6.798m by not implementing safety interventions that cannot be afforded; and
6) Accept the findings of the Equalities Impact Assessment for the Safer Roads Fund projects.
Report author: Joanna Jackson
Publication date: 21/09/2023
Date of decision: 21/09/2023
Decided at meeting: 21/09/2023 - Cabinet
Effective from: 29/09/2023