To seek Cabinet approval to the submission to Government of the Outline Business Case for the Chesterfield-Staveley Regeneration Route.

Decision:

RESOLVED to:

 

1)   Note the issues set out in the report and in Appendices 1 and 2;

 

2)   Delegate authority to the Executive Director – Place, in consultation with the Cabinet Portfolio Holder, Infrastructure and Environment and Section 151 Officer to undertake final amendments to the draft Outline Business Case, prior to submission;

 

3)   Approve the submission the Outline Business Case for the Chesterfield-Staveley Regeneration Route to Government for access to grant funding;

 

4)   Approve the release of £2 million capital receipts, as allocated to the project in June 2022, to fund the next stages of project preparation work; and

 

5)   Authorise officers to commence work on collaboration agreements with public and private sector partners over project funding and risk. 

Report author: Jim Seymour

Publication date: 08/12/2022

Date of decision: 08/12/2022

Decided at meeting: 08/12/2022 - Cabinet